100 Bay State Road – Construction Activity for the period April 28 – May 12

Dear Colleagues & Neighbors:

For April 28  through May 12  you may expect:

The tarp system, which enclosed the building for work during the winter, will continue to be incrementally removed over the next few weeks as exterior walls are finished. Installation of flooring is ongoing. The installation of the masonry façade and back-up components continues and once finished will result in a reduction of the noise from within the construction project site.  When the scaffolding and tarp systems are completely removed, the facade and glass system will be significantly advanced and will serve as a barrier for keeping the sound within the project site. The team of 200 + people working on site every day is working hard to make sure the schedule is met.



View all posts