Law School Intersession Construction Update
Intersession work will begin with equipment mobilization to the site, followed by installation pressure-injected footings and foundation work. Other site prep includes installation of directional signage and temporary access ramps. To enable this foundation work, the outdoor stairs nearest to the Law School (on Marsh Chapel’s west side) will be closed. Pedestrian access to Commonwealth Avenue will be available via stairs and a ramp on the chapel’s east side. Foundation work at the School of Law will continue through the spring.
A third construction trailer will be delivered in January 2013 and will be placed in remaining parking spaces next to the one located on the Bay State Road Extension. All three trailers shall remain for the duration of the project. Parking in the CAS lot will not be impacted by placement of these trailers