Myles Standish Hall – Construction Activity – Week of 6/6/16
For the week of June 6, 2016:
Deliveries
- Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Furniture Donation Load Out – Saturday 6/4/16
- On Saturday, a nonprofit company (Build Health International), will be on site loading out furniture donated by BU that will be shipped to Haiti. All load out will be done on Beacon Street between 7:00 a.m. and 5:00 p.m. Permission and permitting have been secured from the City. Trailers will be dropped off on Friday afternoon and picked up Monday morning.
Man and Material Hoist Construction
- Continue demo of exterior wall off of boom lift on Beacon Street side of building – Exterior.
Demolition Abatement
- Load out at Beacon Street – Load out demo debris from 1st floor to dumpster.
- Continue with demolition of stairway for chute – Interior.
- Basement – Demolition and load out.
- 9th floor buffer zone – Demolition after abatement.
- Abatement of floors 1-9 – Pre-abatement demolition.
- Annex alley demolition – Continue with exterior demolition of one-story addition connected to Annex and demo all exterior MEP attached to façade in the alley – All load out will be by dumpsters in the alley and demolition of addition will be by excavator. A crane will be used to take down the existing duct stacks on the exterior.
Masonry Restoration (Exterior)
- Continue installation of staging on Bay State Road side of building.
- Continue removal of windows on Bay State Road side.
- Continue masonry demo on Bay State Road side.
- Start installation of signage on Beacon Street.
Roof (Exterior)
- Continue with abatement and demolition.
- Continue roof removal and installation of temporary roof curbs.
For questions, please contact Brian Kelley.