Myles Standish Hall – Construction Activity – 7/9/16 – 7/15/16

For 7/9/16 – 7/15/16:

Deliveries

  • Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday 07/09/16

  • Demolition throughout building – Interior
  • Load out of dumpsters on the Beacon Street side of the building – Dumpster will be swapped throughout the day.
  • Activities will require trucks and equipment in the point park area – Access from Bay State Road will be required for dumpsters and equipment.
  • Site work and foundation demolition activities in the Annex alley – Saw-cutting and chipping out concrete and loading into dump trucks for removal.
  • Wood loading dock construction around the base of the man and material hoist on the exterior on the Beacon Street side of the building

Man and Material Hoist Construction

  • Concrete masonry unit (CMU) block infills around gates on all floors
  • Constructing wood loading dock around perimeter of hoist base

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster. Dumpster will be swapped throughout the day.
  • Continue with load out down chute – Interior
  • Demolition and load out of basement
  • Abatement on floors 5, 6, and 7 – Interior
  • Demolition after abatement at buffer zone, floors 3 and 4
  • Demolition of floors 8 and 9
  • Continue with demolition of existing freight elevator and floors 4 and 5 – Interior

Masonry Restoration (Exterior)

  • Continue with masonry demo on the Bay State Road side of the building.
  • Continue installation of CMU at 9th floor along Bay State Road.
  • Start masonry facade demo on the Beacon Street side of building at 9th floor.
  • Start masonry demo on swing above Annex.

Roof (Exterior)

  • Begin layout and installation of CMU at parapet on the Bay State Road side of the building.

Alley Between Annex and Myles at Bay State Road

  • Backfill alley after concrete pour.
    Site work excavation for ramp and utilities in the alley
  • Steel delivery and installation at transformer pad area in alley

Myles 7-8-16 Myles 7-8-16

For questions, please contact Brian Kelley or visit our website.