On Saturday, the following construction work will be occurring onsite from 7 a.m. to 5 p.m.
- Demolition throughout building – Interior
- Load out of dumpsters on the Beacon Street side of building – Dumpster will be swapped throughout the day.
- Installation of steel in the Annex alley between Myles and Annex on the Bay State Road side of building.
- Activities will require workers to be on the roof and trucks and equipment in point park area.