For 7/23/16 – 7/29/16:
Deliveries
- Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday 07/23/16
Permission and permitting have been secured from the City to work from 7 a.m. to 4 p.m.
- Miscellaneous abatement throughout building – Interior
- Complete man and material hoist loading dock on the Beacon Street side of the building.
- Activities will require trucks and equipment in the point park area. Access from Bay State Road will be required for dumpsters and equipment.
- Annex alley – Continue forming transformer pad and vault.
- Annex alley – Continue with excavation for alley underground work. Trucks will be loaded out of alley onto Bay State Road for this work.
Man and Material Hoist Construction
- Inspection
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster, with ongoing daily dumpster swaps.
- Continue with load out down chute – Interior
- Demolition and load out of basement
- Abatement on floors 4 and 5 – Interior
- Demolition of floors 6 and 7 – Interior
Masonry Restoration (Exterior)
- Continue with masonry demo on the Bay State Road side of the building.
- Continue installation of concrete masonry units (CMU) at 9th floor on the Bay State Road side of the building.
- Continue with concrete repairs.
- Continue with masonry facade demo on the Beacon Street side of building the building at 9th floor.
- Continue with masonry demo on swing above the Annex.
- Start installation of relieving angles on the Bay State Road side of the building.
Roof (Exterior)
- Continue with layout and installation of CMU at parapet on the Bay State Road side of building.
Alley Between Annex and Myles at Bay State Road
- Continue with forming for concrete at transformer pad.
- Pour vault walls, equipment pads, and curb.
- Exterior wall framing
- Site work – Continue to bring drain line in off of Bay State Road and into alley.
- Alley – Excavate and start underground electrical and drainage.