For 7/23/16 – 7/29/16:

Deliveries

  • Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday 07/23/16

Permission and permitting have been secured from the City to work from 7  a.m. to 4 p.m.

  • Miscellaneous abatement throughout building – Interior
  • Complete man and material hoist loading dock on the Beacon Street side of the building.
  • Activities will require trucks and equipment in the point park area. Access from Bay State Road will be required for dumpsters and equipment.
  • Annex alley – Continue forming transformer pad and vault.
  • Annex alley – Continue with excavation for alley underground work. Trucks will be loaded out of alley onto Bay State Road for this work.

 Man and Material Hoist Construction

  • Inspection

Demolition Abatement

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster, with ongoing daily dumpster swaps.
  • Continue with load out down chute – Interior
  • Demolition and load out of basement
  • Abatement on floors 4 and 5 – Interior
  • Demolition of floors 6 and 7 – Interior

Masonry Restoration (Exterior)

  • Continue with masonry demo on the Bay State Road side of the building.
  • Continue installation of concrete masonry units (CMU) at 9th floor on the Bay State Road side of the building.
  • Continue with concrete repairs.
  • Continue with masonry facade demo on the Beacon Street side of building the building at 9th floor.
  • Continue with masonry demo on swing above the Annex.
  • Start installation of relieving angles on the Bay State Road side of the building.

 Roof (Exterior)

  •  Continue with layout and installation of CMU at parapet on the Bay State Road side of building.

Alley Between Annex and Myles at Bay State Road

  • Continue with forming for concrete at transformer pad.
  • Pour vault walls, equipment pads, and curb.
  • Exterior wall framing
  • Site work – Continue to bring drain line in off of Bay State Road and into alley.
  • Alley – Excavate and start underground electrical and drainage.

For questions, please contact Brian Kelley.