Myles 12/16/16

For 12/17/16 to 12/23/2016:

Deliveries

  • Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

 Onsite Construction

Saturday Work – 12/17/16 – On Saturday, the following construction work will be occurring onsite from 7 a.m. to 5 p.m. Activities will require workers, trucks, and equipment in the point park. The man and material hoist will be running. The crane will be active on Bay State Road and Beacon Street.

  • Load rooftop equipment with crane at Beacon Street.
  • Removal of staging with crane at Bay State Road and Annex in alley.
  • Clean and stock staging for masons in the Alley, and on the Beacon Street and Bay State Road sides of the building.
  • Interior framing throughout the building.

Verizon Off-Hours Work – 12/18/16 to 12/22/16  – Verizon has informed us that they will be working onsite from 7:00 p.m. to 12:00 a.m. from Sunday to Wednesday. Verizon’s work is unrelated to the project.

Thursday 12/22/16 – On the Beacon Street side of the building the site contractor will be working to bring in a new water main. This work will start at 2:30 p.m. and be completed by 11 p.m. We will need to work out of point park area with trucking to feed this work.

Snow Removal

  • During any snow events snow removal operations could be occurring at all hours in order to keep up with the snow and get site ready for workers. These operations will require equipment, trucking, and manpower.

Demolition

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Demolition of 1st floor (interior).

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue rebuilding exterior façade on the Beacon Street and Bay State Road sides of the building.
  • Continue installation of concrete masonry units on the 1st floor.
  • Continue with installation of windows.

Roof (Exterior)

  • Continue installation of roofing.

Alley Between Annex and Myles at Bay State Road (Exterior)

  • Continue with installation of brick and windows.
  • Eversource will be loading in equipment into the alley on Wednesday 12/21/16.

Site Utility Work

  • Water main tie-in on the Beacon Street side of the building and back fill.