Joan and Edgar Booth Theatre & Boston University Production Center – Construction Activity – July 28, 2017 – August 7, 2017

Joan and Edgar Booth Theatre & Boston University Production Center - Construction Activity - July 28, 2017 - August 7, 2017 7.27.17-1

For July 28, 2017 through August 7, 2017:

  • Permitted by the Town of Brookline and in accordance with the approved Construction Management Plan, authorized work hours are 7 a.m. to 7 p.m. on weekdays, and Saturdays from 8:30 a.m. to 6 p.m. Sunday work schedules must be requested and approved by the Town.
  • Brookline and Boston Police details will continue to be posted at the two construction site entrance gates, one at Essex Street and one at Dummer Street, and the fence along Commonwealth Avenue to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
  • Completion of roofing and interior wall painting in the production wing
  • Air and water balancing of mechanical systems in the production wing
  • Completion of ceiling mounted systems in the flexible theatre
  • Completion of the monumental glass installation at the north side of the building facing Commonwealth Avenue
  • Rigging of ceiling mounted support brackets for the equipment in the flexible theatre is underway
  • Installation of granite facing on the south elevation at Dummer Street
  • Development of the temporary egress stair on Dummer Street

Key Construction Activities

  • Place stone base at production wing exterior walls at select locations beneath the metal panels
  • Complete glass installation at the north façade
  • Spray test curtainwall assemblies at the theatre building
  • Hoist rigging in flexible theatre at ceiling
  • Complete balancing of mechanical equipment in the production wing