Myles Standish Hall – Construction Activity – 8/19/17 – 8/25/17

Myles Standish Hall - Construction Activity - 8/19/17 - 8/25/17 Myles Standish Hall - Construction Activity - 8/19/17 - 8/25/17

For 8/19/17 to 8/25/17:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

 Saturday Work – 8/19/17

  • Coring – Phase 2, floors 6 – 9
  • Clean up staging and site – Phase 2
  • Clean up and loadout – Bay State Road

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue masonry restoration and demolition – Bay State Road & Beacon Street

Roof (Myles – Exterior)

  • Install parapet blocking
  • Coring and sawcutting

For questions, please contact Brian Kelley.

View all posts