For 11/25/17 to 12/1/17:

Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Saturday Work – 11/25/17

  • Caulk windows on Beacon Street
  • Clean up and stocking exterior staging
  • Clean up and loadout

 Demolition/Loadout

  • Load out at Beacon Street and Bay State Road – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps

Masonry Restoration (Exterior – Bay State Road & Beacon Street)

  • Continue with masonry restoration and demolition – Bay State Road & Beacon Street
  • Continue with staging installation and removal

 

Roof Myles (Exterior)

  • Install roof flashing