Myles Standish Hall – Construction Update – 8/3/18
For 8/4/18 to 8/10/18:
Deliveries
- Subcontractors will receive deliveries all week between 7 am and 6 pm on both Beacon Street and Bay State Road
On-site Construction
Saturday Work – 8/4/18 – 7 am to 5 pm
- Clean up and load out
- Interior Work – Myles
- Annex interior framing and MEP roughs
- Annex exterior façade work
- Annex install pavers
Myles – 7 am to 6 pm
Load out
- Load out at Beacon Street and Bay State Road – Load out debris from 1st floor to dumpsters with ongoing daily dumpster swaps
Site
- Myles
- Beacon Street – Continue with cut and caps
- Bay State Road, Beacon Street, and Raleigh Street
- Continue with installation of pavers and landscape
Annex – 7 am to 6 pm
Load out
- Load out at Bay State Road and Beacon Street to dumpsters with ongoing daily dumpster swaps
Masonry Restoration
- Beacon Street, Raleigh Street, and Bay State Road continue with façade restoration