BU Children’s Center – Construction Update – 5/17/19
During the week of May 20th
- Layout and demolition of plumbing trenches in basement will begin.
- Wall demolition at three car garage will begin.
- Construction in progress from sewer line to one garage from Lenox Street.
- Exterior lead abatement will continue using 60’ boom lift.
- Underpinning will continue.
During the Week of May 27th
- Basement slab trenching demolition is continued.
- Single car garage demolition continued.
- Underpinning will continue this week.
- Construction will cut and cap water and provide new water service to main building.
- Interior lead abatement will start this week.
- Exterior lead abatement to continue.
- Window sash and hardware removal to begin this week contingent on release by BU.
- Lead abatement at windows will begin in conjunction.
- Temp window protection after sash removal to begin and follow.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!