During the week of May 20th

  • Layout and demolition of plumbing trenches in basement will begin.
  • Wall demolition at three car garage will begin.
  • Construction in progress from sewer line to one garage from Lenox Street.
  • Exterior lead abatement will continue using 60’ boom lift.
  • Underpinning will continue.

During the Week of May 27th

  • Basement slab trenching demolition is continued.
  • Single car garage demolition continued.
  • Underpinning will continue this week.
  • Construction will cut and cap water and provide new water service to main building.
  • Interior lead abatement will start this week.
  • Exterior lead abatement to continue.
  • Window sash and hardware removal to begin this week contingent on release by BU.
  • Lead abatement at windows will begin in conjunction.
  • Temp window protection after sash removal to begin and follow.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!