Geothermal Well Drilling Initiative – Construction Update – 5/17/19

During the week of May 20th

Park Test Well #3

  • The subcontractor will be remobilizing the drilling rig to clear an obstruction in the bore hole using drill rods and water.
  • After the obstruction is cleared, a testing agency will be on site to measure verticality of the TW#3 by lowering instrumentation on a cable into the bore hole.
  • Towards the end of the week, the drilling contractor will be installing the geothermal piping. This involves connecting and lowering 20’ sections of piping into the bore hole.

Alley

  • No work is scheduled for the alley way.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!