BU Children’s Center – Construction Update – 5/31/19
During the Week of June 3rd
- Interior demolition will continue.
- A fire hydrant will be installed at the site.
- Construction of a sewer line from the one car garage is pending direction from engineers.
- Interior window casings/jambs will be stripped of lead paint.
- Underpinning of main building foundation walls will continue.
During the Week of June 10th
- Basement slab trenching for underground plumbing demolition will begin.
- Stripping interior window casings/jambs of lead paint will continue.
- Underpinning of main building foundation walls will continue.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!