Geothermal Well Drilling Initiative – Construction Update – 5/31/19
During the week of May 31st
Park Test Well #3
- The drilling subcontractor has completely flushed out debris from the borehole and was able to drop a probe to the bottom at a depth of 1500 feet. Construction crew is installing the high-performance geothermal piping within the borehole. Outer piping is anticipated to be compete by 5/31.
- The construction manager has directed the subcontractor to begin installing the inner tubing and temporary well head on Monday, 6/3.
- Pending availability of the testing agent, the construction manager intends to begin continuous 48 -hour conductivity testing to confirm the thermal performance of the TW#3.
Alley
- No work is scheduled for the alley way.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!