BU Children’s Center – Construction Update – 6/28/19
During the Week of July 1st
- Demolition of the three car garage will continue.
- A sewer line will be installed to play support building.
- Concrete layout for elevator at main building will continue.
- Structural framing work at main building will continue.
- Strip lead paint at window openings will continue.
During the Week of July 8th
- On site backfill of the three car garage foundation and preparation for footings will begin.
-
Concrete forms and pour pit footings and walls will continue.
- Structural framing work at main building will continue.
- Strip lead paint at window openings will continue.