Geothermal Well Drilling Initiative – Construction Update – 6/28/19
During the week of July 1st
Parking Lot N
- To provide construction equipment access to the fenced area of the lot, the job site trailer was moved into Granby Parking Lot N, barricades were removed, and grading was modified.
- Within the fenced area, pre-excavation soil materials are being stockpiled for characterization and disposal.
Alleyway
- The site subcontractor will continue to pre-excavate the recorded geothermal well locations laid out by the surveyor to verify utilities.
- A parking restriction notification was issued and the green permit parking signs have been removed from the alley. The signs were replaced with “No Parking Any Time” signs. Temporary fencing to be installed in the alley on 7/1.
- Water storage “Frac” tanks will be mobilized into the alley on 7/2 and 7/3 drilling rig and skid steer equipment will be mobilized for work to begin the week of 7/8.
- Construction equipment will be making multiple trips from the alley to the parking Lot N storage area.
Park
- In anticipation of a drilling operation during the week of 7/8, steel pipe drill casings will be delivered to the site and stockpiled in the park.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!