Geothermal Well Drilling Initiative – Construction Update – 7/3/19

During the week of July 8th

Parking Lot N

  • The crew will install piping for the dewatering discharge which will extended across the east end of the lot to the catch basin on Commonwealth Ave. A temporary ramp will be constructed over the discharge line where it crosses the Commonwealth Ave sidewalk.
  • The site subcontractor will remove trees adjacent to lot N. Parking spaces in the North East corner of lot N will be impacted the tree removal operation.

Alleyway

  • The site subcontractor will continue to pre-excavate the recorded geothermal well locations laid out by the surveyor to verify utilities. Excavated soil materials are being stockpiled for characterization and disposal.
  •  Water storage settling “Frac” tanks were mobilized into the alley on 7/2 and 7/3.
  • Next Tuesday, the drilling subcontractor will begin drilling to bedrock and setting casing at geothermal well location GT-11.
  •  The site subcontractor will begin a tree removal operation in the alley behind the Bay State row houses.
  • Construction equipment from the alley will be stockpiled in the parking lot N storage area.

Park

  • Next Monday, the drilling subcontractor will mobilize the drilling rig on site and begin drilling to bedrock and setting casing at geothermal well location GT-27.On 7/10, a second drill rig will begin drilling through bedrock at geothermal well location GT-27.
  • The site subcontractor will begin a tree removal operation in the park.
  • To access steel bore hole casing material stockpiled in the park, construction will be making multiple trips to the site.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!

View of water storage settling tanks mobilized in the alleyway
View of water storage settling tanks mobilized in the alleyway