Howard Thurman Center – Construction Update – 11/15/19
Week of November 18, 2019
General:
Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking garage and up through the fifth floor is the primary means of access. The existing elevator will continue to remain functional throughout the entirety of the project. All stairwells are available for emergency egress. Temporary emergency egress signs are posted throughout.
Garage Level
- Miscellaneous mechanical, electrical, and plumbing will continue.
- The installation of both the passenger and HTC elevators will continue.
- Removal of temporary fencing will continue.
- Insulation of mechanical duct and piping will continue.
On the 1st Level
- Installation of millwork will continue.
- Installation of vestibule ceiling will continue.
- Installation of interior doors and hardware will continue.
- Installation of drywall at the west vestibule entrance will begin.
- Grinding and floor prep of the public corridor floors will continue.
- Painting of the ornamental ceiling and miscellaneous area will continue.
- Air-handler balancing and testing will continue.
- Miscellaneous HVAC and mechanical will continue.
- Installation of light fixtures will continue.
- HTC stair trim installation will continue.
On the Mezzanine Level
- MEP punch-list will continue.
On the 2nd Level
- Temporary directional signage is placed to help the public navigate.
- Painting touchup and construction in both the common areas will continue.
- Installation of interior doors and hardware will continue.
- Installation of millwork will continue.
- Installation of decorative wave ceiling will begin.
- MEP finish work will continue.
On Levels 3, 4, and 5
- Installation of the fire alarm system will continue.
- The passenger elevator installation will continue.
- Framing of elevator vestibules will continue.
- MEP punch-list will continue.
Exterior
- Caulking and sealant of windows will continue.
- Installation of the arcade pavers will continue.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!