Geothermal Well Drilling Initiative – Construction Update – 1/31/20

During the week of February 2nd:

Parking Lot N

  • The drilling subcontractor will be pressure testing the piping within the completed boreholes.

Alleyway

  • The drilling subcontractor will be pressure testing the piping within the completed boreholes.

Park

  • The drilling subcontractor will be pressure testing the piping within the completed boreholes.
  • Construction equipment will be making periodic trips into the fenced area of the park to access the stockpiled soil materals for removal.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!