Goldman School of Dental Medicine – Construction Update – 1/31/20

During the weekend of February 1:

  • On Sunday, night-shift work will continue, starting at 10 p.m. and continuing until 6 a.m., during which workers will be installing new telecommunications services—telephone and data communications—in the existing GSDM building; activities will include transferring the telecommunication service to connections throughout the new north and west additions.

During the week starting February 3:

Floor by floor progress:

  • On the first floor of both the seven-story west and two-story north additions, workers will continue installing lighting and completing the ceiling in the auditorium. Installation of furniture and audio-visual equipment will also continue.
  • On the second, fourth, fifth, sixth, and seventh floors of the seven-story west addition, final painting touch-ups will be made and furniture placement will continue. Crews will be installing audio-visual equipment throughout these floors.
  • On the third floor of the seven-story west addition, work will continue on installing the simulators in the new Simulation Learning Center.
  • City of Boston inspections for Phase 2 will continue next week following a successful week of tests on the new fire pump and generator. This week’s focus will be on testing the new stair pressurization system, a system designed to keep smoke out of stairwells during an emergency, allowing occupants of a building to exit safely (as required by law for a high-rise building).

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!

The nearly completed student, resident, faculty, and staff entrance, East Newton Street
The nearly completed student, resident, faculty, and staff entrance, East Newton Street
Finishing touches on the brand-new GSDM auditorium
Finishing touches on the brand-new GSDM auditorium