During the week of February 10th :

Parking Lot N

  • No geothermal work is scheduled.

Alleyway

  • The drilling subcontractor will be pressure testing the piping within the completed borehole at GT-11 at the east end of the alley.

Park

  • No geothermal work is scheduled.

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!