CFA Renovations – Construction Update – 2/21/20
During February 21st – February 28th:
(Please note that there is work scheduled for Saturday, February 22nd)
General:
Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the Concert Hall. Stair access directly off Commonwealth Ave will be open and closed periodically as construction continues and signage will indicate status. The central stair is always available for emergency egress.
Exterior:
There is work scheduled for this Saturday, February 22nd. This work will consist of the installation of relieving angles at the southwest corner of the building.
East Façade
- Work on the installation of the ramp and handrails continues through the end of the month.
- Paving will begin after the ramp is completed.
South Façade
- Removal of the staging on the southwest façade will continue through the end of the month.
West Façade
- Removal of the staging is set to begin and will be ongoing through the first week in March.
North Façade
- Repairs to the window jambs have begun and will continue into mid-March.
Archways
- Installation of the glazing in the archways the 1st floor of the building is ongoing and expected to be completed by the end of March.
Interior:
On the Ground Level
- The welding and installation of piping in the mechanical rooms continues and is expected to be completed by the end of the month.
On the 1st Level
- Demolition of the art gallery floor has begun and will be rebuilt over the remainder of the month.
- The installation of the vitrines in the art gallery is ongoing through the end of the month.
- Painting in the student lounge has begun and will be ongoing throughout the remainder of the month.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!