During the weekend of August 1st

Excavation for the podium foundations
  • The site will be open for construction activities on Saturday; crews will continue installation of the H-Piles for the crane pad.
  • Installation of the inclinometers will continue. The inclinometer is used to monitor the movement of the support of excavation sheets as excavation continues.

During the week of August 3rd

  • Installation of the H-Piles for the crane pad will continue using the hydraulic hammer to drive the piles the remaining ten feet into bedrock.
  • Excavation for the building foundations will continue. This activity will continue in the “podium” portion of the building, closest to Sargent College.
  • Installation of cross bracing for the support of excavation system will be installed as excavation continues.
  • Installation of the inclinometers will continue.
  • As activity in and around the site begins to increase, please be aware of all directional signage, as pedestrian travel paths may be altered.