During the weekend of October 10th

  • On Saturday, crews will be on-site to continue with the excavation in the tower portion of the building, along with the installation of bracing for the support of the excavation system.

During the week of October 12th

  • Excavation continues in the tower portion of the building. Material is being removed down to the third level of cross bracing, which is approximately 30 feet down from the previous parking lot grade.
  • The installation of the third level of cross bracing for the Support of Excavation (SOE) system is being installed as soils are removed and the working area is available.
  • The installation of rebar and formwork continues for the foundation walls at the podium.
  • Please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up to date information via these notifications.