Center for Computing & Data Sciences – Construction Update – 10/23/20

Continued excavation in the tower

During the weekend of October 24th

  • On Saturday, crews will be on site to continue with the installation of bracing for the Support of Excavation (SOE) system.

During the week of October 26th

  • In the tower, excavation has been completed down to the third level of bracing for the SOE system.
  • The installation of the third level of cross bracing for the SOE system will continue.
  • In the podium, the installation of rebar and formwork for the foundation walls will continue with the focus currently being on the south wall. A concrete pour of this wall is scheduled for the end of the week.
  • Waterproofing of the tower foundation walls will begin and crews will begin applying the membrane at the east wall.
  • Please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up to date information via these notifications.
Rebar and formwork for the foundation walls in the podium