Center for Computing & Data Sciences – Construction Update – 12/11/20
Concrete placement ongoing for the podium’s ground floor slab
During the weekend of December 12th
On Saturday, workers will be on site to continue installing rebar and formwork for the tower’s core from the sub-basement to the lower level.
During the week of December 14th
Removal of the lowest level Support Of Excavation (SOE) bracing will continue.
Backfilling around the podium foundation walls will continue.
The installation of rebar and formwork for the 3-tiered stepped slab will begin at the transition from the podium to the tower. The lower tier stepped slab is scheduled for concrete placement towards the end of the week.
Rebar and formwork installation will also begin at the exterior foundation walls in the tower.
Please be aware of all directional signage, as pedestrian travel paths may be altered. We will continue to provide you with up to date information via these notifications.