Center for Computing & Data Sciences – Construction Update – 12/3/21
During the weekend of December 4th
On Saturday, crews will continue installation of rails and platforms for elevators 4, 5, and 6 in the tower’s core. Activities for intumescent and spray fireproofing of the columns and beams on the upper floors of the tower, and installation of mechanical, plumbing, and fire protection rough will also continue. Crews will be on site receiving curtain wall materials, assembling panels, and preparing clips for installation.
Crews preparing for curtain wall and roofing installation
During the week of December 6th
Installation of curtain wall panels will begin at the ground floor of the tower and will continue working up the building over the next few months.
In the subbasement and lower level, crews from the mechanical, electrical, and plumbing (MEP) subcontractors will continue installing the MEP systems. Drywall installation will also continue.
On floors 2 through 19 of the tower, the MEP subcontractors will continue installing electrical conduit, hangers, and piping.
Crews will continue applying a fireproof coating to the interior steel beams and columns along with a white fireproof coating for the tower’s 17th, 18th, and 19th-floor framing.
The elevator subcontractor will continue installing equipment, rails, and platforms for elevators 4, 5, and 6, located on the south side of the tower’s core.
In the podium, installation of above-ceiling sprinkler pipe, ductwork, plumbing pipe, and electrical rough-ins will continue on the 2nd, 3rd, and 4th floors. Wall framing will continue throughout.
Installation of the roofing system at the podium will continue.
Trucking activity to and from the site will be occurring daily with trucks entering and exiting the designated gates.