During the week of March 13th

  • Minor metal stud framing and electrical work will continue this week, and mechanical rough-in will begin.
  • The team is planning for an electrical inspection and rough framing inspection that is expected to take place mid-week. Once inspection is complete, insulation and sheetrock installation will begin.
  • Sheetrock will be delivered to the site on Wednesday, 3/15/23. A spotter will be with the delivery truck at all times.