West Campus Dining Expansion – Construction Update – 3/31/23
Project Updates
- Contractor began the installation of sheetrock following the rough-in inspection and sign off.
- Work on the overhead mechanical systems continued.
- The Sonotube placement for the footing of the new canopy was completed, along with the removal and block infill of an existing exterior door.
Week of April 3rd
- Continuation of sheetrock installation and mechanical rough-in.
- Delivery and installation of the new canopy. A police detail will be on-site for the delivery of the canopy to ensure pedestrian safety in the plaza.
- Cutting of the exterior concrete wall for the new building entrance. Please note that this work is scheduled for Friday, April 7th and will be very noisy.