West Campus Dining Expansion – Construction Update – 3/31/23

Project Updates

  • Contractor began the installation of sheetrock following the rough-in inspection and sign off.
  • Work on the overhead mechanical systems continued.
  • The Sonotube placement for the footing of the new canopy was completed, along with the removal and block infill of an existing exterior door.

Week of April 3rd

  • Continuation of sheetrock installation and mechanical rough-in.
  • Delivery and installation of the new canopy. A police detail will be on-site for the delivery of the canopy to ensure pedestrian safety in the plaza.
  • Cutting of the exterior concrete wall for the new building entrance. Please note that this work is scheduled for Friday, April 7th and will be very noisy.