- The contractor is nearing the completion of the sheetrock installation and the mechanical rough-in work.
- Sheetrock tapping has begun.
- The ACT ceilings in the egress corridor will be removed this Saturday, April 8th.
- Structural steel installation for the canopy has begun. Once done, the removal of the exterior concrete wall will begin.
Week of April 10th
- The sheetrock installation and taping will be completed, as well as the mechanical rough-in work.
- The removal of the exterior concrete wall will be completed.
- Installation of the rooftop condensing unit will begin.