West Campus Dining Expansion – Construction Update – 04/28/23

General Project Updates

  • The rough HVAC install has been completed.
  • Brick repairs at the new entrance have been made.
  • The metal deck at the exterior part of the entrance has been welded, and the canopy posts have been installed.
  • Wood framing on the ceiling of the canopy has been completed.

Weekend of April 29th

  • The ceiling tile grid is set to be installed in the hallway outside of the temporary wall.
  • Millwork is being installed.
  • Temporary protection will be put in place.

Week of May 1st

  • Tile flooring installations to be completed.
  • Carpet and VCT installation continues.
  • Mechanical, electrical, and plumbing finishes to be installed.
  •  Electrical above-ceiling finishes being installed.
  • Fire alarm programming (new devices) to take place.
  • Millwork installation continues.
  • Fire sprinkler installation continues.
  • Above-ceiling inspection will take place at the end of the week.
  • The team will begin the layout of the exterior site work.
  • The dumpster exchange is scheduled for Monday, 5/1.
  • The fire sprinklers will be shut down on Tuesday, 5/2, and Wednesday, 5/3.