West Campus Dining Expansion – Construction Update – 04/28/23
General Project Updates
- The rough HVAC install has been completed.
- Brick repairs at the new entrance have been made.
- The metal deck at the exterior part of the entrance has been welded, and the canopy posts have been installed.
- Wood framing on the ceiling of the canopy has been completed.
Weekend of April 29th
- The ceiling tile grid is set to be installed in the hallway outside of the temporary wall.
- Millwork is being installed.
- Temporary protection will be put in place.
Week of May 1st
- Tile flooring installations to be completed.
- Carpet and VCT installation continues.
- Mechanical, electrical, and plumbing finishes to be installed.
- Electrical above-ceiling finishes being installed.
- Fire alarm programming (new devices) to take place.
- Millwork installation continues.
- Fire sprinkler installation continues.
- Above-ceiling inspection will take place at the end of the week.
- The team will begin the layout of the exterior site work.
- The dumpster exchange is scheduled for Monday, 5/1.
- The fire sprinklers will be shut down on Tuesday, 5/2, and Wednesday, 5/3.