West Campus Dining Expansion – Construction Update – 2/10/23
General Project Updates
Work continues in the Claflin Hall Residence Life offices, including make safe of the electrical, plumbing, and mechanical systems.
Last weekend, a temporary wall was constructed to separate the work zone from the public lobby.
The construction crew also installed site fencing in the West Campus Plaza, the east end of Claflin Hall, and have created a separate and secure access for construction personnel.
The temporary wall installed in the lobby.
During the week of February 13th
This week will see demolition work continue in the Residence Life offices and the installation of additional site signage.