West Campus Dining Expansion – Construction Update – 2/10/23

General Project Updates

  • Work continues in the Claflin Hall Residence Life offices, including make safe of the electrical, plumbing, and mechanical systems.
  • Last weekend, a temporary wall was constructed to separate the work zone from the public lobby.
  • The construction crew also installed site fencing in the West Campus Plaza, the east end of Claflin Hall, and have created a separate and secure access for construction personnel.
The temporary wall installed in the lobby.

During the week of February 13th

  • This week will see demolition work continue in the Residence Life offices and the installation of additional site signage.
Site fencing in the West Campus Plaza.