West Campus Dining Expansion – Construction Update – 03/24/23
Interior Work Last week, the electrical rough-in work was completed and inspected. The metal stud framing was also completed and is […]
Kilachand Hall Phase 2 – Construction Update – 03/24/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 03/17/23
General Project Updates The past week consisted of metal stud framing, rough electrical and ductwork, and piping for HVAC in the […]
Kilachand Hall Phase 2 – Construction Update – 03/03/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
Kilachand Hall Phase 2 – Construction Update – 02/24/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 02/17/23
General Project Updates Work continues on the renovations to the Residence Life offices. Interior demolition continued during the week of the […]
Kilachand Hall Phase 2 – Construction Update – 2/17/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
Kilachand Hall Phase 2 – Construction Update – 02/10/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 2/10/23
General Project Updates Work continues in the Claflin Hall Residence Life offices, including make safe of the electrical, plumbing, and […]
Kilachand Hall Phase 2 – Construction Update – 02/03/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]