Kilachand Hall Phase 2 – Construction Update – 01/20/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
Center for Computing & Data Sciences – Construction Update – 01/20/23
During the weekend of January 21st On Saturday and Sunday, crews will be on site delivering and assembling furniture. Also […]
Kilachand Hall Phase 2 – Construction Update – 01/13/23
General Project Information Daily Work Hours from 7 am – 3 pm. Classes are back in session on 1/17. The […]
Center for Computing & Data Sciences – Construction Update – 01/13/23
During the weekend of January 14th On Saturday, crews will be on site delivering and assembling furniture. On Saturday and […]
Kilachand Hall Phase 2 – Construction Update – 1/6/23
General Project Information Daily Work Hours from 6 am – 3 pm. The team will be starting at 6 am […]
Center for Computing & Data Sciences – Construction Update – 1/6/23
During the weekend of January 7th On Saturday, crews will be on site delivering and assembling furniture. Crews will also […]
Center for Computing & Data Sciences – Construction Update – 12/22/22
During the weekend of December 24th On Saturday, crews will be on site delivering and assembling furniture. During the week […]
Kilachand Hall Phase 2 – Construction Update – 12/22/22
General Project Information Daily Work Hours from 6 am – 3 pm. The team will be starting at 6 am […]
Kilachand Hall Phase 2 – Construction Update – 12/16/22
General Project Information Daily Work Hours from 8 am-4 pm. (Quiet study and exam period) The Traffic Management Plan for […]
Center for Computing & Data Sciences – Construction Update – 12/16/22
During the weekend of December 17th On Saturday, crews will continue the installation of the finishes on the lower floors […]