Author: Lauren Alzate
West Campus Dining Expansion – Construction Update – 01/27/23
During the week of January 30 Monday, 1/30 – Install temporary fencing at the west end of Claflin Hall (grassy […]
West Campus Dining Expansion Comments/Questions
Kilachand Hall Phase 2 – Construction Update – 1/27/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
Center for Computing & Data Sciences – Construction Update – 10/21/22
During the weekend of October 22nd On Saturday, in the interior of the building, crews will continue installation of the […]
Kilachand Hall Phase 2 – Construction Update – 10/21/22
General Project Information Daily Work Hours from 7 am – 3:30 pm. The Traffic Management Plan for the project has […]
Center for Computing & Data Sciences – Construction Update – 9/23/22
During the weekend of September 24th On Saturday, on the exterior of the building, crews will be working from the […]
Kilachand Hall Phase 2 – Construction Update – 9/23/22
General Project Information Daily Work Hours from 7 am-3:30 pm. The Traffic Management Plan for the project has been approved […]
Kilachand Hall Phase 2 – Construction Update – 7/29/22
General Project Information Daily project work hours have been adjusted to start as of the week of 7/11: Now 6am-3:30pm […]
Center for Computing & Data Sciences – Construction Update – 7/29/22
During the weekend of July 30th On Saturday, crews will be working from the elevated platforms continuing the installation of […]
Center for Computing & Data Sciences – Construction Update – 1/14/22
During the weekend of January 15th On Saturday, crews will continue buildout of elevators 4, 5, and 6 in the […]